Neumeyer Environmental Services, Inc. - Remediation - Materials Management - Construction Support
Environmental Services

Asbestos Management
   Inspections
   Surveys
   Abatement

Lead Compliance
   Training
   Testing
   Abatement

Chemical Management
   Heavy Metals
   Inorganics
   PCBs
   Petroleum Products
   Organics

Storage Tank Services
   Testing
   Cleaning
   Removal & Demolition
   Containment

Water Management
   Water Quality
   Wastewater Management

Radiological

Structural Demolition

Construction Support
   Construction Monitoring
   Well Monitoring
   Construction Surveys
   Sampling and Analysis
   Waste Characterization
   Regulatory Compliance
   Site-Specific Plans

Health & Safety Training




Balfour Beatty Infrastructure - PennDOT Settlers' Cabin Interchange - Pittsburgh, PA - 2005 - $235,000

Scope of Work:
Construction of a new highway interchange required demolition of two large commercial buildings. One was a metal framework structure covered with 60,000 square feet of asbestos panels; it had been used as a distribution warehouse for industrial rubber products. The second building had housed a sales and processing operation for a water treatment company. In addition to 4,000 square feet of asbestos containing materials (ACM) in floors, roofs, and insulation materials, the building contained 500 tons of hazardous caustics and acids that had been used for water treatment.

At the rubber products warehouse, Neumeyer Environmental coated each asbestos siding panel with encapsulant to seal in any loose asbestos fibers. The 300 pound panels were unbolted, lowered to the ground, wrapped in plastic sheeting and placed in a roll-off containers. The ACM was transported to a regulated facility for disposal. After completion of the abatement, Neumeyer Environmental demolished the building.

In the water treatment building, Neumeyer Environmental drained and flushed all tanks and piping and collected the chemicals in containers provided by the DOT. We shipped the chemicals to a hazardous waste processing facility. Neumeyer Environmental removed and disposed of the ACM from the structure and demolished the building.

Neumeyer Environmental recycled 800 tons of structural steel and provided 3,000 tons of crushed concrete for use as roadway base material.



Removal of asbestos-containing window systems, exterior view


Removal of asbestos-containing window systems, interior view



Home xxxxxxx About Neumeyer xxxxxxx Contact xxxxxxx Qualification Statement xxxxxxx Related Links