by neumeyeradmin neumeyeradmin

Golden Triangle Construction
Murrysville and Delmont, PA – 2005-2009 – $1,000,000

Scope of Work:
Neumeyer Environmental conducted an abandoned oil and gas well closure in accordance with PADEP requirements to prevent migration of contaminants into the adjacent soils, atmosphere and waterways. Neumeyer Environmental constructed access to the site, installed erosion and sediment controls including a sediment pond to collect the well cleaning decant. We remove the piping and casing during grout placement to ensure an adequate seal was establishes. NES place the standpipe and restored the site to pre-existing conditions.

Approximately one year after closure, the well began leaking from an unidentified production zone based on well records. Neumeyer Environmental remobilized and performed investigations and resealing of the well.